Prior to placing a tank into operation, which tests should be completed?

Prepare for the Pennsylvania Underground Storage Tank (UST) Certification Exam through interactive quizzes featuring flashcards and multiple-choice questions. Each question is accompanied by hints and comprehensive explanations to enhance your knowledge.

Prior to placing a tank into operation, it is essential to conduct functional and operational tests to ensure that the tank, as well as its associated systems, are working as intended. Functional tests verify that the tank's components, such as pumps, alarms, and monitoring systems, operate correctly. Operational tests assess whether the system can handle various operational scenarios, including product delivery and dispensing. These tests help identify any potential issues before the tank is actively used, therefore reducing the risk of spills, leaks, or operational failures that could harm the environment or public safety.

While inspections and specific tests like tightness testing or monitoring groundwater may be vital throughout the life of a UST, they do not encompass the broader need to confirm the entire system's functionality and readiness for operation.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy